Quality control
Pre-shipment inspections and AQL: a practical guide to quality control at source
By Hurugo · · 4 min read
Once goods leave the factory, your leverage over quality falls sharply. A defect found during production is a conversation; the same defect found in your warehouse is a write-off, a return, or a damaged reputation. Quality control at source exists to catch problems while they can still be fixed, and AQL sampling is how professionals do it consistently.
The four types of inspection
- Pre-production inspection. Checks raw materials and components before production starts, so problems are caught before they are built into every unit.
- During-production inspection. Takes place once part of the order is complete, typically early in the run, so issues can be corrected for the rest of the order.
- Pre-shipment inspection. The most common check. It takes place once production is complete and most of the order is packed, so the inspector sees finished goods in their final packaging.
- Container loading supervision. Confirms the right goods, in the right quantity, are loaded properly and the container is sealed.
For a first order with a new supplier, consider combining a during-production inspection with a pre-shipment inspection. For established suppliers with a good record, a pre-shipment inspection alone is often enough.
What AQL means
Inspecting every unit of a large order is slow and expensive. Instead, inspectors check a random sample and decide whether the whole lot passes, using the acceptance quality limit (AQL) method set out in the international standard ISO 2859-1.
Two inputs set the sample size: the size of the lot and the inspection level. General inspection level II is the usual default. The AQL you choose for each class of defect then sets how many defects the sample may contain before the lot fails.
Critical, major, and minor defects
| Class | What it means | Common AQL |
|---|---|---|
| Critical | Unsafe, or breaks a legal requirement | 0 (no defects accepted) |
| Major | Likely to cause a return or complaint | 2.5 |
| Minor | A small flaw that is unlikely to cause a return | 4.0 |
These are common starting points for consumer goods, not fixed rules. Tighten them for premium products, and agree them with your supplier in writing before production begins, so a failed inspection is never a surprise.
What a pre-shipment inspection checks
- Quantity: the number of finished and packed units against the order.
- Workmanship: visual defects such as scratches, stains, loose threads, or poor finishing.
- Conformity: materials, colours, dimensions, and weights against the specification and the approved sample.
- Function and safety: on-site tests suited to the product, from assembly and operation checks to basic electrical safety tests.
- Packaging and labelling: carton markings, barcodes, inserts, and labelling, including South African requirements.
- Transit readiness: carton drop tests and checks that packaging will survive the journey.
How to prepare for an inspection
An inspection is only as good as the standard it checks against. Before booking one, put together a clear product specification, the approved golden sample, a list of known defects to look for, the AQL levels for each defect class, and any functional tests you want performed. Share it with both the supplier and the inspector.
What to do when a lot fails
- Review the report to understand whether the failure is isolated or systematic.
- Ask the factory to sort and rework the goods, removing or repairing defective units.
- Re-inspect before shipment. Agree in advance who pays for re-inspection, usually the supplier.
- Negotiate only once the facts are clear. Accepting a failed lot at a discount can be reasonable for minor defects, but never for critical ones.
Do not release the balance payment until the goods pass. That payment is your strongest leverage, and it disappears the moment the money is sent.
How Hurugo manages quality
Quality control at source and standard operating procedures with suppliers are built into every project we manage, as step five of our six-step process. Every Soshida and Balvaro product we sell goes through the same checks.
Frequently asked questions
When should a pre-shipment inspection take place?
Once production is complete and most of the order, commonly at least 80%, is packed. This lets the inspector check finished goods in their final packaging while there is still time to fix problems before shipment.
What does AQL 2.5 mean?
AQL 2.5 is the acceptance quality limit used to decide how many defects of a given class a sample may contain before the lot fails. It is a common level for major defects in consumer goods. The exact number of defects allowed depends on the sample size.
Who pays for a product inspection?
The buyer usually pays for the first inspection. It is common to agree in the purchase order that the supplier pays for any re-inspection after a failure.
Is a pre-shipment inspection worth it for small orders?
Usually, yes. An inspection costs little compared with the value of most orders, and a single avoided problem pays for many inspections.